the following projects require access to the tunnel:

-installation of the active grid.
-installation of the linear motor and sled. (Lambertz) 
           3-6 weeks, start: end of november
-installation of the camera systems. (Dr. Xi)
-installation of the laser system.
-installation of the new floor. (Dr. Xi)
          ? weeks, start: after the installation of the motor
-performance of passive grid turbulence measurements.
          4 weeks, start begin of november 
-installation of the new ceiling
-installation of the laser positioning system (Lambertz)
          1-2 days, parallel with the installation of the linear motor
-installation of the wires for the motor (Lambertz)
          1 week, parallel with the installation of the linear motor
-installation of the wires for the aktive grid

-fix the design of the sled

    - pressure tubes (Dr. Xi)
    - holding system for the mirrors (Dr. Xi)


time schedule

-week 44: installation of the end 
-week 45-48 (2/11/2009 - 29/11/2009) : experiment, Dr. Bewley
-week 49- 52 (1/12/2009 - 23/12/2009 : installation of the linear motor (Schminke, Lambertz) 
-week 53 (24/12/2009 - 4/1/2010)
-week 1-3 (5/1/2010 - 24/1/2010): installation of the linear motor (Schminke, Lambertz)